Kenya has yet to conclude the termination of its controversial contract with Indian firm Adani, two years after the government announced the cancellation. New disclosures by the PPP Directorate say the delay could increase the amount the company has been seeking from Kenya.
Adani signed a contract in October 2024 with the Kenya Electricity Transmission Company (Ketraco) to build three electricity transmission lines and substations under a public-private partnership. President William Ruto directed that the contract be cancelled a month later, in November 2024, yielding to public pressure.
“The termination of the contract between Ketraco and Adani for the Transmission Lines project, which commenced in the 2024/25 financial year, was still ongoing as at the end of the 2025-26 financial year,” the PPP Directorate said in a new report.
Adani obtained the contract after giving Ketraco a privately initiated proposal to expand power infrastructure. The company would build three transmission lines totalling 371 km, including the 206-kilometre, 400kV Gilgil-Thika-Malaa-Konza line, and three substations. The projects were estimated to cost Sh95.68 billion. Adani would then operate and maintain the infrastructure for 30 years and charge electricity consumers to recover its investment.
Ketraco, which has previously built and operated power transmission infrastructure, is paid wheeling charges by Kenya Power to move electricity from power plants to the distribution network. Those charges are passed on to consumers. Besides transparency concerns and the failure to put the proposal through public participation, Kenyans also worried about the effect on the cost of power, noting that the wheeling charge might be higher than what taxpayer-funded Ketraco is paid.
In an earlier report, the PPP Directorate said the project was cancelled before it reached financial close, following the “disqualification of the proponent due to new information on their credibility”. In his 2024 State of the Nation Address, President Ruto directed the cancellation, citing new information from investigative agencies and partner nations. Adani was then facing bribery charges in the United States. Those charges were dismissed in August 2026.
Kenya is expected to pay Adani Sh5 billion for cancelling the contract. The stalled exit has raised fears of a repeat of Ketraco’s ongoing Sh10 billion debt crisis with Spanish contractor Instalaciones Inabensa SA.
In April 2013, Ketraco awarded Inabensa two contracts to build the 127-kilometre, 400kV Lessos–Tororo transmission line, which would link the power grids of Kenya and Uganda, and to expand the Lessos substation. Ketraco terminated the contracts in April 2016 over alleged non-performance. The Spanish firm blocked the hiring of a replacement contractor in court and also took a case to an arbitral tribunal.
The tribunal ruled in 2019 that Ketraco had unlawfully breached the contract and ordered it to pay Inabensa €37.37 million (Sh5.4 billion), with 12 per cent annual interest from the date of the award. Ketraco lost appeals through to the Supreme Court, and compounding interest took the debt to Sh10 billion. An October 2026 High Court ruling stripped Ketraco of state immunity and cleared the way for the firm to pursue liquidation proceedings against the utility.
Adani had been expected to play a significant role in Kenya’s PPP programme. The government had also handed Jomo Kenyatta International Airport to India’s Adani Airport Holdings for an upgrade and expansion, but that arrangement was likewise cancelled after public uproar and the firm’s indictment in the United States on bribery allegations. The Adani power infrastructure project is among four cancelled projects for which the government is set to pay the contractors for terminating the contracts.