Tonopah, Nevada — Crescent Dunes, an Obama-era solar plant about 13 miles northwest of Tonopah, roughly halfway between Las Vegas and Reno, has gone bankrupt a second time and sold for $7 million. The isolated plant sits on a 2,250-acre federal site in barren desert. More than 10,000 mirrors surround a 640-foot tower.

American developer SolarReserve developed the project. Spanish contractor Cobra, a subsidiary of construction group ACS, built it. Both held ownership stakes in Tonopah Solar Energy, the company that owned the plant. Spanish bank Banco Santander also held an ownership stake. Then-Senate Minority Leader Harry Reid, a Nevada Democrat who died in 2021, championed the project and in 2016 called it an engineering and clean energy marvel, predicting Nevada would benefit for decades.

Unlike ordinary panels, the plant focuses sunlight onto a receiver, heating molten salt to roughly 1,050 degrees Fahrenheit. The salt stores heat so steam can drive a turbine after sunset. It was the first commercial-scale U.S. solar tower to use molten salt both to collect and store heat. The Department of Energy projected 482,000 megawatt-hours a year and a maximum output of 110 megawatts, enough for more than 75,000 Nevada homes at peak.

The Obama administration backed it with a $737 million federal loan guarantee and about $275 million in Treasury grant awards, within a broader $90 billion push after the 2008 crisis. The financial collapse comes 15 years after Solyndra, another Obama-backed solar company, left taxpayers with a $528 million loss, a sum Crescent Dunes’ estimated tab could nearly match.

Commercial operations began in late 2015. A major molten-salt tank leak in October 2016 shut the plant down less than a year later. During that shutdown, Treasury approved a cash-grant payment in March 2017. The plant returned in July 2017, but performance stayed weak. In 2018, its best full year through 2025, it produced 41 percent of the DOE’s projected annual output, according to federal energy records. Another tank failure stopped generation in March 2019. Seven months later, NV Energy ended its 25-year power contract. The first bankruptcy followed in July 2020.

That restructuring handed ownership to ACS through affiliate Crescent Dunes Investment, with Cobra running the plant. The turnaround plan aimed at 400,000 megawatt-hours a year, more than twice the plant’s best annual output. It restarted in July 2021, then further tank leaks in 2022 and 2023 forced more shutdowns. It sold power under shorter contracts, kept losing money and relied on support from affiliated companies, court records show. By January 2026 it was in bankruptcy again. Mississippi-based Sons of Liberty Construction, owned by three brothers, bought it for $7 million in July and is trying to revive it. During a Fox News Digital visit the plant was generating electricity, though the buyers said output remained well below the original target. Fox News Digital contacted ACS Group and its attorneys and received no response.

SolarReserve co-founder and former chief technology officer Bill Gould told Bloomberg in 2020 that the failure was a tragedy of mismanagement, accusing ACS Cobra of delaying work and designing a defective molten-salt tank. An unnamed engineer who said he had worked there since early development gave a similar account in SolarPACES in 2023, blaming tank failures on design and welding and saying the solar collection technology had comparatively few problems. He said the old conventional thermal equipment was having the troubles.

Oliver Hemmers, a physicist who formerly led the Harry Reid Center for Environmental Studies at the University of Nevada, Las Vegas, told Fox News Digital that larger molten-salt tanks make the materials challenge harder. Temperature swings of hundreds of degrees can crack the metal. He had not reviewed the engineering plans and questioned how thoroughly the tank design was tested, noting that other solar-thermal plants use several smaller tanks. When operations resumed in July 2023, operators cut the hot-salt tank from about 1,050 degrees Fahrenheit to about 850, later raising it to as high as 900. Lower temperatures cut electricity output and revenue. Cheaper photovoltaic panels, including panels made in China, undercut the project. The same pressures have hit California’s Ivanpah plant, another Obama-era heliostat project that cannot store heat for power after dark.

DOE said it settled its interest in the 2020 bankruptcy to maximize recovery and estimated its loan loss at $232 million, a figure it confirmed to Fox News Digital on background. DOE assistant press secretary Caroline Murzin said in a written statement that previous administrations irresponsibly managed taxpayer dollars in support of what the department called the Green New Scam, and that since 2020 DOE has had no ownership, operational or financial interest in the project. A separate Treasury grant award of $275.6 million was not meant to be repaid if program rules were met. Combined with DOE’s estimated loan loss, that would put the federal cost at about $507.6 million, although Treasury has not confirmed the full grant was disbursed and DOE has not given a final accounting of loan losses. Fox News Digital has filed Freedom of Information Act requests with both departments. The grant is also the focus of a private investor lawsuit alleging construction companies fraudulently secured the money. A judge dismissed the case at the Justice Department’s request, and the investors are appealing.

Rep. Lance Gooden, a Texas Republican, told Fox News Digital that Crescent Dunes is a microcosm of what he called wrong with Democrat governance, citing wasted taxpayer money, fraud and a cover-up. Economist Véronique de Rugy of George Mason University’s Mercatus Center said government should not pick winners and losers and argued that politicians do not personally bear the losses. Nick Loris, president of the Conservative Coalition for Climate Solutions, said the financing was a risky bet on technology meant to address solar intermittency and should be weighed against the wider loan portfolio. DOE has cited California’s 550-megawatt Desert Sunlight panel farm, which a 2024 assessment said was meeting its loan obligations. In its fiscal 2027 budget justification, DOE reported that through Sept. 30, 2025, borrowers had paid nearly $5 billion in interest, compared with nearly $1 billion in default losses. Hemmers said the project started too expensive, then hit technical problems, and that it completely failed in the end.